1. Fill out Monitor ranks [ongoing]
2. Graymoor Friary–yearly availability to be determined
22. RPH Well - MAJOR PRIORITY!
16. Determine status of Caretaker Agreement for Nuclear Lake...seems lost at NPS
46. Work with NPS and ATC to acquire Revolutionary Hut Site property on Canopus Hill Road adjacent to Inoculation Station:
19. Review of water supply issues [ongoing]...
3. Management Plan 5 year update –
4. Resolution of remaining acquisitions and survey needs –
21. HVPC ATV access...Still more work to be done on this:
21a. Depot Hill Access Road - locks and keys.
20. Verizon Route 20 project –
24. Upgrade well pads - [Concrete base under well, so splash water goes away from well and doesn’t go back down hole]
25. Bulletin board redesign and replacement
27. Have another look at Hiller Brook realignment possibilities and debris removal
47. [New 1/04] 500+ feet of puncheon/boardwalk needed at north end of Hammersley Ridge (town of Pawling) from the green trail to the yellow trail
44. Overall weak blazing along trail – 2005 priority
14. D/P AT Brochure: Were able to go through 2003 with existing stock of D/P brochure – pick up in 2005 for Fall 2005 [change address for TC, etc.]; NYNJTC needs to budget for this for October 2005.
12. West Dover Oak protection from parking...
33. Open Field mowing: ONGOING project
13. Nuclear Lake interpretational sign... check with possibility of NPS funding [reactivated 2005]
39. Add a Pawling side trail– now that the Town of Pawling has purchased Holiday Hills YMCA, reopen discussions with the Town to implement a side trail from Telephone Pioneers shelter to Holiday Hills, and perhaps to Murrow Park.
40. Work with DOT to convert the hiker crossing signs at major roads to the new bright yellow design.–need to contact the current Regional Maintenance Engineer. Jim Haggett will follow through.
29. Planning for buildings for Messerschmitt.
31. Wheelchair Access for Nuclear Lake, using access road to dam area.- also see item 35 below.
32. Improve parking areas for Long Hill Road:
35. Parking around Old Route 55/Route 55 intersection – Jane continues to research this...
35a. Problem with dumping on the other side of Old Route 55.
42. [suggested by Tim Messerich and Mark Hudson] Tent platform(s) at Stewart; iceberging [to keep tents in designated sites]
43. Route 52 Parking Lot–erosion problems [both AT and side trail from parking area]:
Need to monitor for continuing/future problems.
HOLD (No action planned at present, but project may resurface)
11. Schagticoke [11/03: Move to HOLD status–may be impractical and/or unnecessary?]
15. Nuclear Lake Campsite...MOVED TO PERMANENT HOLD – THIS PROJECT DROPPED!
* concerns with sanitation and water supply issues
31. Research alternative privy designs for RPH, HELD due to extreme cost
23. Hoyt Road relo...may not be necessary since it’s dried out?
17. Routed AT crossing signs... Crafted by Fred Gerty
**. Canopus Hill waterbars, sidehilling
**. Taconic Parkway approach–complete repair of new trail route
5. Cleanup of Hiller Brook old boardwalk materials - Completed during May 4, 2003 Mitzvah Day; materials still remain in foundation east of Railroad tracks.
8. TP Shelter Privy relo completed November 8, 2003
10. Corbin Hill Planting (done) for 2003 - survival status of top Corbin Hill field plantings-- about 1/3
37. Middle-height bridge railing for the Duell Hollow bridge. [Done in early 2003]
36. Gutter for Wiley shelter. Completed 10/2003
34. Relocation around Old Route 55, near Peni house site. Done 2003 by Jim Haggett.
4c. [Remaining survey needs] Confirmed survey completed for additional Schagticoke acquisition(s) [done in 2003].
21b. Jane Geisler needs to install a lock at Hoyt Road ....
28. Steps for west side of County 20...Mike Arthur led a trip on 4/25/04 and completed the project.